WEEK 09 Stage 2 · Hands-on lab 10 hours
Control Logic and PID
DELIVERABLE Working DP-reset sequence
Week progress0%
Learning objectives
- >Model a simple hydronic loop with a pump curve and a system curve
- >Implement and tune a PI loop for DP control
- >Implement trim-and-respond DP reset, lead/lag rotation and alarms
- >Estimate pump energy savings with the affinity laws
Sessions
Three 2-hour weeknight sessions plus a weekend block. Check each one off as you finish it.
Quiz
Score: 0 / 5 · aim for 4+
Answer in your notebook first, then reveal the answer and grade yourself honestly.
-
Q1Pump speed drops from 100% to 70%. By the affinity laws, roughly what share of full power is used? Why are real savings usually lower?
[ reveal answer ]
About 34% (0.7³). Real savings are lower because of fixed DP setpoints, static head, and VFD and motor efficiency losses. -
Q2What symptom tells you a loop's proportional gain is too high?
[ reveal answer ]
The loop oscillates or hunts around setpoint. -
Q3What happens if the integral time is too short? Too long?
[ reveal answer ]
Too short: overshoot and oscillation. Too long: a slow return to setpoint. -
Q4Why rotate lead and lag pumps?
[ reveal answer ]
To equalize wear and run hours, and to prove the standby pump works. -
Q5Why can't you reset the DP setpoint all the way to zero?
[ reveal answer ]
The most demanding branch still needs enough pressure to reach design flow.
// DONE WHEN
// STRETCH (OPTIONAL)
Rebuild the loop in CODESYS structured text.