WEEK 05 Stage 1 · Concepts 9 hours
Reading Controls Documents
DELIVERABLE Spec scope summary, I/O count
Week progress0%
Learning objectives
- >Navigate Division 23 09 00 and Division 25 controls specifications
- >Read control schematics, points lists, network risers and panel layouts
- >Explain the submittal → checkout → functional testing → turnover flow
- >Compare plans-and-spec, design-build and owner-direct delivery
Sessions
Three 2-hour weeknight sessions plus a weekend block. Check each one off as you finish it.
Quiz
Score: 0 / 5 · aim for 4+
Answer in your notebook first, then reveal the answer and grade yourself honestly.
-
Q1What is the usual difference between a Division 23 09 00 controls spec and a Division 25 spec?
[ reveal answer ]
23 09 00 is HVAC controls under the mechanical contract. Division 25 covers integrated automation, often bid separately or owner-direct. -
Q2What is the difference between point-to-point checkout and functional performance testing?
[ reveal answer ]
Point-to-point checkout verifies each I/O point's wiring, scaling and response. Functional testing verifies that sequences perform as written. -
Q3Which part of a CSI spec section usually lists approved manufacturers?
[ reveal answer ]
Part 2, Products. -
Q4Name three red flags you might find in a controls specification.
[ reveal answer ]
Examples: sole-source or proprietary-only requirements, no trending or graphics requirements, vague sequences, no training or warranty terms, and unclear integration responsibilities. -
Q5On a plans-and-spec job, who is the controls contractor's direct customer?
[ reveal answer ]
The mechanical contractor.